Guide
Choosing a G100 export-limitation scheme
What a Customer Limitation Scheme is, when a job needs one, and the choice
that matters — inverter-integrated or a
stand-alone device — with what the DNO sees either
way.
What a CLS is
A Customer Limitation Scheme (ENA EREC G100) is equipment
that holds the net current at the connection point within a
declared ceiling — a Maximum Export Limit (MEL) for
generation, a Maximum Import Limit (MIL) for demand. It works on the net flow:
the house can generate far more than the limit as long as the balance leaving the
premises stays under it, with the scheme throttling the inverters when it
wouldn’t.
Why bother? Because the DNO plans its network around what can flow at the
connection point, not what is bolted to the wall — and G99’s SGI
procedures reward a capped export with a lighter process for a bigger
installation:
- SGI-2 — up to just under 32 A of installed
generation per phase (each unit ≤ 16 A), with a scheme limiting export
to ≤ 16 A.
- SGI-3 — up to just under 60 A per phase (each
unit ≤ 32 A), with a scheme limiting export to
≤ 32 A — waived entirely when the aggregate is
already ≤ 32 A.
One thing a scheme never does is turn G99 into G98: the G98/G99 boundary is
Registered Capacity only (see the registered-capacity guide). The scheme decides
which G99 procedure, not whether G99.
The choice: inverter-integrated or a stand-alone device
- Inverter-integrated — the proposed inverters
themselves are the CLS, using their built-in limitation function with
a CT at the connection point. No extra hardware — but every proposed
inverter must be registered on the ENA Type Test Register as a Fully
Type Tested G100 CLS (the register answers yes/no on every entry).
The claim is printed: G100 Form A lists those inverters’ register
references as the CLS, under the customer’s signature, so CLRD
refuses an inverter-integrated scheme on any proposed inverter the register
doesn’t back — and the picker shows a CLS chip so you can see it
before choosing.
- A stand-alone device — a separate ENA-registered
limiter (the register’s “Stand-alone G100 Device” category)
that holds the connection point within the limit by itself,
monitoring the supply at the connection point — no integration with the
inverters, and no reliance on their own limitation functions. The
device’s own register reference is what Form A declares, and CLRD
prints it on the form and labels the limiter box on the single-line diagram
with it. A stand-alone device is the route when the
inverters aren’t CLS-registered, when existing units are part of the
picture (an existing inverter is never the new CLS), or when the same device
should also hold an import limit — one device can carry
both directions, declared as a shared export/import limiter.
Fail-safe by design
G100’s type testing is mostly about what happens when things go wrong,
which is why the register flag matters more than a datasheet claim:
- Normal operation — the scheme modulates generation
so the net export stays within the MEL.
- Excursion — a temporary breach must be pulled back
within 1 minute (3 minutes for slow-acting devices).
- Failure — if a component or its communications
fail, the controlled devices must trip or fall to a safe power level within
10 seconds. The scheme fails safe, or it isn’t a
scheme.
What the DNO sees
- G100 Form A rides the application: the CLS’s
register reference(s), the MEL per phase, and the customer’s signature.
- G100 Form C rides the post-install pack: the CLS
installation and commissioning tests, confirming the scheme does what
Form A declared. Domestic type-tested schemes are commissioned
unwitnessed — the DNO doesn’t attend; the paperwork is the
assurance.
- The approval may come back lower. A DNO can grant less
export than was applied for (zero is a valid answer). CLRD records the granted
figure with the approval, and the post-install pack states the limit the
scheme was actually commissioned to, while the application keeps what it asked
for.
In CLRD
Declare the scheme in the wizard’s Export Limitation section —
inverter-integrated, or a stand-alone device picked from the register with its
reference frozen onto the job. CLRD enforces the CLS register check on
inverter-integrated schemes, applies the SGI-3 waiver automatically, routes the
G100 forms onto the right packs, and draws the limiter (with its reference and
limit) on the single-line diagram. An import scheme is declared alongside in the
same section — the same stand-alone device or its own — and adds the
same Form A / Form C pair wherever the export scheme
hasn’t already.
References
- ENA EREC G100 (Issue 2, 2022) — the Customer
Limitation Scheme standard: operational states, fail-safe times, and the
Form A / Form C paperwork.
- ENA EREC G99 (Issue 2, 2025), §6.2.2.3–.4
— the SGI-2 and SGI-3 procedures whose eligibility rides on the
scheme.
- ENA Type Test Register — the per-device G100 CLS
flag, and the Stand-alone G100 Device category.