Taking the loop impedance measurements SSEN trade for a G99 SGI-3 fast track — the method their procedure prescribes, the 180 mΩ threshold, and the readings and photographs their form FO-NET-CAB-008 records. UK Power Networks ask for the same reading on an unlimited SGI-3 application, with no form and no published threshold: the method is the same, and CLRD files the readings for them on its own Loop Impedance Measurement Statement, no photograph needed.
An SGI-3 application is the largest of the G99 Small Generation Installation procedures — aggregate generation approaching 60 A per phase, export-limited to 32 A — so before approving one the DNO must be satisfied the local network can absorb the export. The phase-to-neutral loop impedance at the premises is a direct measure of how electrically strong that supply is: the lower the impedance, the smaller the voltage rise the exported current causes on the network.
Every other GB DNO runs that assessment itself, from its own network records. SSEN instead accept a measurement taken at the premises by the installer, notified on their form FO-NET-CAB-008 under their procedure PR-NET-CAB-004 — and an SGI-3 application carrying a qualifying measurement takes the fast track instead of waiting on a full design study. The form is optional: without it the application still goes in, and SSEN assess it the slow way.
None of this touches the national framework. The measurements are SSEN’s own ask, the threshold is SSEN’s own figure, and neither changes which G98/G99 documents a job needs — CLRD’s routing never reads them.
PR-NET-CAB-004 (§6) permits connection under the fast track where the phase-to-neutral loop impedance is below 180 mΩ. At or above it, the application goes the normal SGI-3 route and SSEN run a full design study — CLRD tells you which side a reading falls as you type it, and either way the job proceeds: the verdict is information, never a block.
SSEN’s own form prints the limit as “180 mΩ or less” while their procedure says below 180 — the two disagree at exactly 180.0. CLRD takes the procedure’s stricter reading, and a result that close to the line is worth re-testing anyway: lead placement and contact resistance move a milliohm-scale reading more than you’d think.
In CLRD you don’t need to work this out: the SSEN Fast Track panel appears on the Pre-Install Application card exactly when the job qualifies. No panel, no test to take.
SSEN’s letter offers the test or an export limitation scheme holding export to 3.68 kW; UKPN’s offers the reading or a normal A1-1 application. Filed with neither, every such application came back three to four weeks later asking, and the operator’s clock ran again from the answer. So CLRD asks before the application is generated: while the question is open a recommendation at the top of the job page says the operator requires the test to process the job and carries the two buttons below, the section is Required, and Generate waits until you do one of three things.
Before submission both buttons are an ordinary Revise: the earlier details are archived with the job, the documents regenerate, and the job page says what was done. Once the application is with the operator, press Amend: the amendment puts the same three choices — the operator is going to ask, so you can generate and submit the amended application before or after their letter comes — and the reading, if you take it, is recorded on the amendment and rides the amended pack. An amendment is the only way CLRD changes or adds to an application the operator already holds.
SSEN prescribe the method exactly, because a reading taken any other way is wrong in a way nobody can spot afterwards:
Never remove the SSEN cut-out fuse to take any of these readings — it is SSEN’s sealed equipment, and the incoming-isolator method exists precisely so their fuse stays in place. And keep the declared figures honest to the display: SSEN may re-measure, and a phase-to-neutral reading more than 5% off what was declared may be treated as a breach of the procedure (§7).
Open the SSEN Fast Track panel on the Pre-Install Application card and record the readings, whether the meter reported the prospective currents, and the meter photograph; add the cut-out photograph in its own section of the same card. The fast-track verdict shows beside Save as you type the phase-to-neutral figure. (On a UK Power Networks job the panel is Loop Impedance Test, asks for the readings alone, and gives no verdict — UKPN have published no threshold. If UKPN asked after the application went in, press Amend, record the readings on the amendment, generate it and submit it: the statement goes to them with the amended application.)
CLRD holds the form out of the application until every reading and both photographs are recorded, because an incomplete FO-NET-CAB-008 voids the application — SSEN allow 7 working days to supply what’s missing before they take the measurements themselves and recharge the cost (§5). Complete, the filled form files with the G99 A1-2 automatically — there is nothing else to attach.